4 February 2005 Reconstruction Of Circle Line MRT Tunnels And Station At Nicoll Highway
29 January 2005 Work on the Nicoll Highway Station will resume in the middle of 2005. It will be located about 100m from its original site near Java Road.
4 December 2004 Re-Opening Of Nicoll Highway
30 November 2004 Temporary Closure Of Nicoll Highway

More 



 

All buildings that are near LTA worksites are constantly monitored to ensure that they are structurally sound and safe for use. LTA ensures that its contractors puts in place a comprehensive set of equipment to monitor any movement. Instruments such as settlement markers, electrolevel beams and inclinometers are installed in these buildings, with readings taken at regular intervals.

Following this incident, there has been much interest in the safety procedures during construction of road and rail projects. We would like to assure you that we place much emphasis on safety during the course of our work. There are also stringent measures in place when awarding contracts.

If you want to learn more about how we carry our construction projects, read on. There are four stages in this process:

1. Planning stage
2. Tender stage
3. Design stage
4. Construction stage




Stabilising the incident site

Several safety measures were put in place on site immediately after the incident. Firstly, a damaged canal within the collapsed area was blocked up to prevent the flowing in of tidal water from Kallang River. Canvas sheets were also placed on the surrounding slopes and open areas to protect the soil. We had also filled the cracks around the site with grout to prevent water seepage.

These efforts were put in place to prevent further movement within the collapsed area. It was also vital to see to the safety of the rescue personnel and the adjacent structures.

Keeping Merdeka Bridge Safe

Efforts were also underway to ensure the stability of nearby Merdeka Bridge. The section of the bridge nearest to the incident site was cut off to prevent its remaining structure from being weakened. Once this was completed, Crawford Underpass, which is directly below the bridge, was re-opened on 29 April 2004. Read more about the separation process and history of the bridge here.




Safety reviewed at all other sites

Excavation works at all other CCL sites were put on hold pending a safety review of the temporary works.

Engineers who had designed the temporary works have been asked to check and confirm to our Building Control Unit (BCU) that these designs are safe. In turn, these designs have also been sent to the Building & Construction Authority (BCA) for their review. BCA has also conducted site visits to ensure that the temporary support structures and monitoring measures are securely in place.

Excavation works only resume once all safety aspects are found to be in order. On 15 May 2004, BCA completed the review of four CCL stations, which were given the green light to resume excavation. They were Dhoby Ghaut, Convention, Millenia and Harbourfront stations.

Another four stations, Museum, Paya Lebar, Kim Chuan Depot and Old Airport Road stations, were allowed to resume excavation works on 24 May 2004. On 4 June 2004, excavation works at four more stations resumed, following the completion of BCA's review. These were Marymount, Bishan, Serangoon and Upper Paya Lebar stations. Another two stations were given the all-clear on 14 June 2004. They were Tanjong Katong and MacPherson stations.

At our own initiative, works at Paya Lebar, Tanjong Katong and Old Airport Road stations have been suspended pending the review of the design of temporary works. These stations are being built by the same contractor overseeing works at Nicoll Highway station.

The remaining four CCL stations, namely Bartley, Lorong Chuan, Boulevard and Nicoll Highway, are still being reviewed.


Going beyond what’s required

We recognise the complex nature of our projects and are committed to incorporate more stringent safety requirements into our contract documents. We also have various safety measures in place, over and above what are required under the Factories Act.

As a firm believer of the Safety First philosophy, we work closely with the contractors to see this through. Some examples of what we do:

Contractors are required to conduct in-house Safety Induction Course (SIC) for all workers before they are allowed to work on site. This is to familiarise them with hazards specific to their assigned scope of work.

Before proceeding with critical work on site, all contractors are required to submit method statements outlining work and safety procedures, together with assessment of the construction risks. This ensures that they have given due consideration to safety of the work to be done.

Contractors are also required to inspect the cranes every 6 months, instead of yearly as stated under the Factories Act.

We have also put together an Occupational Safety & Health Management (OSHM) manual and a Project Quality Management System (QMS). Besides listing key safety programmes and work processes, they also stipulate that a risk management process must be performed at various stages of the project, i.e. at Concept Design, Detailed Design and Construction stages. This way, all identified potential hazards can be recorded and we can thus track the mitigating measures to eliminate, or reduce, these hazards to an acceptable level.

Regular safety exercises on issues such as working at heights and preventing objects from dropping are also conducted on sites.




There were seven stages to the whole process of rebuilding the highway so that construction of Nicoll Highway Station could resume. This took about seven months.

The 1st Stage
The 2nd & 3rd Stages
The 4th & 5th Stages
The 6th & 7th Stages
 



  

Ministry of Manpower
   
Building & Construction Authority
 






At about 3.30pm, the temporary wall supporting the excavation site for the tunnels leading towards the Nicoll Highway MRT station along Circle Line Stage 1 collapsed. This resulted in major soil subsidence and the caving in of a section of Nicoll Highway. LTA staff arrived on-site soon after the incident occurred to assist with rescue and recovery works. At the time of the incident, the contractor, Nishimatsu Construction Co. Ltd/ Lum Chang Building Contractors Pte Ltd Joint Venture was carrying out excavation works for the construction of tunnels.

The incident had resulted in 4 fatalities. No motorists were travelling along that section of Nicoll Highway when the incident happened.

Click here for further details.

Last Updated on 04/02/2005

Conditions of Access | Copyright © Land Transport Authority 2003 | Privacy Statement
Best viewed with IE 5.0 & above, 800x600 Resolution