|

The 1st Stage
On 23 April 2004, LTA proceeded to fill the collapsed site with
‘foam’ concrete. This type of concrete can flow into
the small voids between the debris and displace the water that had
seeped into the excavation.
Filling the site with concrete served to stabilise the void and
prevent further soil movement and subsidence of the surrounding
areas. The low strength of this concrete mix allows it to be removed
later when excavation resumes following the recovery process.

The 2nd & 3rd Stages
Several days later on 27 April 2004, a mixture of soil and cement,
were poured into the site to form a level platform.
After the ground in the collapsed site had stabilised, we concentrated
our efforts on stabilising the outer areas of the collapsed slopes.
That was the third stage of the recovery work. The outer slopes
were filled with mass concrete. Once this was done, a delicate operation
to remove debris at the top commenced. On 14 May 2004, cranes were
brought in to clear the debris, which included a crane boom and
several steel beams. These had to be cut into smaller pieces before
they could be moved. This intricate process took about two months
to complete.


The 4th & 5th Stages
The stretch of Nicoll Highway was rebuilt on bored piles to strengthen
the new road to withstand changes in soil conditions. Re-building
on bored piles also means that the new road will not be affected
by future excavation works. Reconstruction works began on 24 August
2004. Fifty-seven bored piles were sunk 50m into the ground to support
the 150-metre new road.
After that, concrete slabs were cast followed by tarring. Structures
such as streetlights were then added before the road was re-opened
on 4 December 2004. Reconstruction of Nicoll Highway took about
three months, and motorists are now able to travel on the highway.
Take a look at how the reconstruction works were carried out here.

The 6th & 7th Stages
Backfilling of the affected area at the Nicoll Highway MRT worksite
has been completed. The ground level has been restored to its original
pre-excavation level.


|