|
LTA
works closely with various agencies to plan and develop land transport
infrastructure in Singapore. When doing so, measures to minimise the impact
of our works on the environment are also discussed. During the construction
of our roads and rail system, due consideration is given to minimise environmental
impact to existing mature trees as well as noise generated from road traffic.

LTA is committed to protecting our environment. We incorporate
environmental protection in our strategic decisions and conduct our business
in a manner that balances the environmental and economic needs of the
communities in which we operate.
We will:
 |
Comply
fully with all relevant environmental legislation and regulations
and meet or exceed good environmental practices; and |
 |
Work with our partners i.e., transport
operators, contractors, interest groups and other government agencies
in a concerted effort to operate in an environmentally responsible
manner. |

LTA places great emphasis on raising awareness in incorporating environmental protection
measures through education and promotion. Since year 2007, we have published the following guidebooks:
 |
Best Environmental Practices: Earth Control Measures (published in January 2007) |
 |
Best Environmental Practices: Noise Control at LTA Sites (published in July 2008) |
The guidebooks aim to equip our staff and contractors with the various control techniques as well as best practices
which they may adopt on site.


Even
during the early stages of our projects, careful planning is being carried
out to minimise the number of affected trees and when it is not possible,
we work with the relevant agency to plant new trees.
Read more about our efforts to go green for some of
our projects here:

The National Environment Agency (NEA) is a party which LTA
works closely with on environmental concerns. To ensure that nearby residents
and businesses are not affected by construction works, noise pollution
levels generated are monitored and kept within levels determined by the
NEA.
Where possible, we plant more trees between the roads and
residential units to reduce the impact of our works on the environment.
Equipment designed to keep noise and vibrations to a minimum are also
used. Barriers are placed near residential areas where possible, and much
planning is also carried out to schedule works at appropriate time periods.

To minimise inconvenience to public and to reduce the impact of construction activities to residents living near the KPE site, noise, dust and other mitigating measures were implemented.

Geylang River
Engineers carefully diverted the Geylang River, laid the KPE in its place, before shifting the river back to its original alignment.
Kallang Practice Track
The tunnel construction method allowed for the preservation of the Singapore Sports Council's field track along Kallang.

Pelton Canal
By following the alignment of the Pelton Canal below ground level, the KPE removed the need to create a visually obtrusive elevated viaduct which would have affected the privacy of the lower floor units in surrounding HDB flats.
Read more about our conservation and environmental for the KPE

LTA requires contractors to submit his schematic ECM plans of the construction
site for the contract duration endorsed by Qualified Erosion Control Professional (QECP) and install
the ECM according to the QECP’s design.
During construction, the Contractor is required to minimize the formation of bare
surfaces using the following measures:
Contractor is also required to install and maintain sediment control measures and facilities
which include:
| a) |
Minimise site disturbance by keeping site clearance works to a minimum by retaining as much of the existing vegetation as possible. |
| b) |
Pave up the bare surfaces and all construction access by concrete or milled waste or other suitable materials |
| c) |
Protect the bare slopes with close-turfing, concrete grouting, canvas or erosion control blanket
|
| |
|
| d) |
Protect the earth stockpiles with canvas or erosion control blanket |
| e) |
Restore ground cover over disturbed areas, which are or have become bare, as soon as possible
|
| |
|
| f) |
Carry out trench excavation work in sequence with the progress of permanent works to minimise impact on the environment |
Contractor is also required to install and maintain sediment control measures and facilities
which include:
| a) |
Concrete-lined cut-off drains along the perimeter of the construction sites |
| b) |
Erect silt fences in front and along the perimeter cut-off drain along the perimeter of the boundary of the site
|
| |
|
| c) |
Install intermediate silt traps along the perimeter lined cut-off drain
|
| |
|
| d) |
A treatment system using chemical coagulants or membrane system shall be installed
to treat all silty discharge before the discharge points into public drain
|
| |
|
| e) |
Use of polymer blocks in sedimentation tanks, silt traps and along perimeter drain. |
| f) |
Install a turbidity and total suspended solids (TSS) monitoring device for continuous
monitoring of the TSS and turbidity of the discharge into the storm water drainage system |
| g) |
For construction works near water bodies, turbidity curtains must be installed. The design,
fabrication, and installation of the primary and secondary turbidity curtains must be conducted
to ensure that the turbidity of water in the water bodies around the works shall not exceed the
pre-existing levels or 50mg/l |

LTA requires contractors to submit a noise management plan sufficiently in advance of the Works
Sensitive buildings are identified and mitigation measures implemented before work commences
Noise Measurements
Prior to the commencement of any construction activities, contractors are required to carry out a survey of the noise
levels for one week, on a 24-hour basis, to establish the levels of the background noise for record purposes.
Noise measurements are required for buildings within 50m from the contract limits. Noise levels
at buildings shall be measured 1m away from the nearest façade of the building to the road and readings shall be taken
from at least 3 different levels.
Noise Controls
Contractors are required to take all practicable steps to reduce noise arising from site activities to the minimum.
These steps include:
| a) |
All machinery and plant must be sound reduced prior to entering the site
|
| |
|
| b) |
Noisy plant must be housed in an acoustic shed
|
| |
|
| c) |
Noisy activities must be barricaded with portable sound barriers/panels |
| d) |
Noise barriers should be erected before noisy work commences if the site is within
proximity to residences and/or sensitive buildings
|
| |
|
| e) |
Establish good rapport with the community |

Contractors are required to:
| a) |
Use source reduction and effective drainage as the main forms of mosquito control. |
| b) |
Apply larvicides or mosquito oil to supplement source reduction. |
| c) |
Have an in-house pest control team to search and destroy any potential breeding
grounds, especially after every rainfall, using the “zoning method” (see below for more
details on the zoning method). |
| d) |
Engage NSRS (National Skills Recognition System) certified pest control operators. |
| e) |
Carry out thermal fogging when necessary
|
Zoning Method

Last Updated on 15/08/2008
|