LTA has made steady progress on the North–South Corridor (NSC), which will enhance connectivity from the northern region to the city. As of August 2026, more than 90% of the viaduct foundation works have been completed, with construction progressing to above-ground structures such as columns, crossheads and viaduct segments installation. For the tunnel section, over 90% of the foundation works have also been completed, with major excavation works ongoing across the 12.3km alignment.
2 As major structural works at the surface-level are completed, commuters and motorists can look forward to progressive improvement of travel conditions along the corridor and reinstatement of roads and footpaths previously occupied by construction activities.
Significant Construction Challenges
3 As construction progressed, we also encountered several site-specific challenges, such as challenging ground conditions, and the complexity of carrying out works in close proximity to existing roads, major utilities and operational MRT infrastructure. These include:
a. Gambas Avenue and Woodlands Avenue 8: More significant foundation works were needed due to utilities and challenging ground conditions encountered during viaduct construction works, such as harder and higher rocks which necessitated longer time to complete the piles than originally planned. With the foundation works nearing completion, construction can progress to the next stage of above-ground works, including the launching of large viaduct segments across existing roads, major junctions and operational MRT infrastructure.
b. Novena: Due to fractured rock and groundwater inflows underneath the live North-South Line (NSL) tunnel, we had to use a more precise and time-intensive mining method of excavating in smaller sections, instead of direct tunnelling as originally planned. This approach took longer as it involved continuously removing rocks, grouting and adding supports to advance works. However, it was necessary to prevent soil movement or settlement that would have affected the live operations of NSL and live traffic in Novena. This is one of the most technically demanding sections of the project, where the NSC tunnel passes both above and below the operational NSL, with clearance as close as 1 metre. These works have to be carried out in extremely constrained conditions and require careful planning, sequencing and monitoring to ensure the continued safety and reliability of MRT operations.
c. Thomson: Site investigations revealed harder-than-expected rock formations and highly variable ground conditions. LTA had to conduct extensive controlled rock blasting, additional rock removal and ground stabilisation works before excavation could proceed safely. The construction methodology and earth-retaining systems also had to be revised to suit the ground conditions and to ensure the stability of the excavation.
4 Details on these challenges are provided in the Annex.
Impact on Construction Timeline
5 As construction for the NSC at each stage is dependent on the one before, the works must be carefully sequenced to keep workers and the public safe. The full extent of delays at these critical work fronts, and its knock-on impact on subsequent activities (including the construction of columns, crossheads and viaduct segments), only became clearer as works progressed and actual ground conditions were established. Despite our efforts to expedite works safely and optimise construction methodologies, the challenges we faced has cumulatively resulted in an approximately two-year increase in the overall completion timeline.
6 Following detailed assessments of these cumulative impacts and the additional measures required to safely complete the remaining works, LTA determined that more time would be needed to safely complete the remaining works. The NSC viaduct from Admiralty Road West to Lentor Avenue is now expected to open in phases from 2029, instead of 2027. The tunnel section from Lentor Avenue to East Coast Parkway (ECP) is expected to open in phases from 2031, instead of 2029.
Progressive Reinstatement of Roads Ahead of NSC Opening
7 While the opening timeline for the NSC has been revised, commuters and motorists travelling along the corridor can expect travel conditions to improve progressively as major structural works are completed. From 2027, more construction activities will move underground, reducing surface-level construction and easing disruption on surrounding roads. From 2028, roads, footpaths and other adjacent areas occupied by construction will be progressively reinstated for public use. This means that as works are completed, construction disamenities can be reduced when spaces along the corridor are progressively reinstated ahead of the NSC’s opening.
8 In the meantime, LTA and its contractors will continue to deploy additional manpower and equipment where effective, optimise construction sequences and prioritise critical activities to make up time where feasible.
9 We recognise that the revised timeline will prolong construction impact for residents, businesses, motorists and commuters along the NSC corridor, and appreciate the public’s patience and support as we work through these challenges. We will keep residents, businesses and other stakeholders updated on upcoming works and traffic arrangements, as we work to complete the NSC safely and deliver its long-term benefits to commuters, motorists and communities along the NSC.