Changi-Simei, Bedok And Marina Bay To Have Cycling Infrastructure By 2014

News Releases 15 Jul 2010 cycling infrastructure cycling town Cycling Facilitation Committee (CFC) cycling paths

1. In line with the National Cycling Plan, the Land Transport Authority (LTA) has been facilitating the development of dedicated off-road intra-town cycling paths in towns all over Singapore where there is strong community support for cycling.

2. In February 2009, a plan to roll out a $43-million intra-town cycling programme in 5 HDB towns - Yishun, Tampines, Taman Jurong, Pasir Ris, Sembawang - was announced. Construction of dedicated cycling paths in Tampines and Yishun has started early this year. The first 1.2km stretch in Tampines will open for use on 18 July 2010. Works for the cycling paths in all five towns are expected to be completed by 2012.

3. On top of these 5 towns, LTA will now embark on developing dedicated cycling paths in Changi-Simei and Bedok towns. These cycling paths complement the existing cycling infrastructure within these HDB towns and facilitate intra-town cycling to transport nodes and key local amenities. They will progressively be implemented by 2014.

4. "Cycling is a more environmentally-friendly, cost-effective and healthier mode of transport. With the dedicated off-road cycling paths in place in HDB towns, residents can cycle from their homes to transport nodes and key local amenities, while workers can cycle from transport nodes to their workplaces in the vicinity. LTA will continue to work with the community to identify suitable towns which can benefit from having such cycling infrastructure," said Mr Teo Ser Luck, Senior Parliamentary Secretary for Transport and Community Development, Youth and Sports.

Cycling Infrastructure in Marina Bay

5. LTA has been working closely with the Urban Redevelopment Authority and National Parks Board to implement a network of cycling paths in Marina Bay. The proposed cycling paths in Marina Bay is one of the initiatives proposed under the Sustainable Development Blueprint announced in 2009, to plan for an overall sustainable transport system in Marina Bay.

6. The cycling network in Marina Bay will be developed in phases, in tandem with the development of the area. By 2014, cyclists can look forward to 16 km of cycling paths within Marina Bay. The remaining cycling network in Marina Bay will be put in place as the area is developed further.

7. Please refer to Annex A for the implementation timelines of the cycling paths in the five HDB towns selected earlier and in Marina Bay.

Cycling Facilitation Committee Recommendations

8. A Cycling Facilitation Committee (CFC) led by Mr Teo Ser Luck was formed in June 2009 to establish a common, community-led approach to key "soft" issues arising from the implementation of cycling infrastructure in HDB towns.

9. The CFC recognises the importance of safe cycling and gracious cycling behaviour and has made several recommendations, which can be achieved through public education and enforcement efforts.

10. For more details on the recommendations made by CFC, please refer to Annex B.

Scroll To Top

Welcome to the

new LTA.GOV.SG


This quick tour will bring you through the key enhancements.

Use the links at the top navigation bar to help you find what you are looking for


Jump straight into the popular pages that

are most relevant to you


Taking a bus, train, or cycling to your

destination? Plan your routes and check

the fares using these tools!


Our latest featured projects are just a click away!


Start exploring the new

LTA.GOV.SG now!



Explore Now!